Gas Liquids Engineering Ltd. (GLE) provided complete EPCM services for the installation of a gas battery and pipeline for Iteration Energy’s North Boundary 15-31-88-14-W6M wellsite. Installed equipment included:
- Two (2) RJV 8” Lo-Flo Separator Packages
- 697 metre long pipeline, 114.3 mm (4 NPS) outside diameter, Grade 359 Cat 2 YJ-1
- Tie into separator discharge at 11-31-88-14-W6M