Gas Liquids Engineering Ltd. (GLE) completed EPCM services for the detailed design of the 4 MMSCF/d Pine Creek sweet gas plant for Talisman. Installed equipment includes:
- Wellhead
- Sand Separator with Bypass
- Three-phase Inlet Separator with Gas, Condensate & Water Metering with Allowance for Condensate Blow
- Case & Methanol Injection
- Two (2) 400 bbl Water Storage Tanks
- One (1) 50 bbl Pop Tank
- RTU Panel
- Diesel Generator for Heat Tracing
- Remote Wireless Transmitters
- Designed for future HP & LP Dual Flare Stack with FKOD
- Connections for Future P-Tank Tie-In for Flow Back